August 22, 2010

WINDOWS ARE DONE. DRYWALL IS DRY.

DSC06358After more than a month delay, the custom front and back windows are in.  The team can now finish the trim, siding and weatherproofing.  The coming week will be finishing all the wood stairs, installing most of the cabinets and then the floor finishing can begin.  Next up is ordering carpet, arranging delivery of the rest of the appliances and getting the last of the paint colors chosen.  We’re more delayed than we would like (early October move in now) but things are looking good and it’s fun to see it all come together.