WINDOWS ARE DONE. DRYWALL IS DRY.

DSC06358After more than a month delay, the custom front and back windows are in.  The team can now finish the trim, siding and weatherproofing.  The coming week will be finishing all the wood stairs, installing most of the cabinets and then the floor finishing can begin.  Next up is ordering carpet, arranging delivery of the rest of the appliances and getting the last of the paint colors chosen.  We’re more delayed than we would like (early October move in now) but things are looking good and it’s fun to see it all come together. 

August 1, 2010

FLOORS!

DSC06334The bulk of the American walnut flooring is in and it’s looking good – even without being finished.  Drywall as all been primed and the wood stairs are being made.  Still waiting on the custom windows for the front and back (over a month late) but optimistic that they will show up before the crew has to stop working.  The September 15 completion date is a little risky if the windows don’t arrive within the next couple weeks.